2000

1 March 2000: The tablet bearing the site information

27 March 2000: Beginning of construction work


12 April 2000: First level of the pit is reached

26 April 2000: More effort on stabilization of existing buildings required


4 May 2000: Remove the old foundations

10 May 2000: Lowering the ground-water level


16. May 2000: Deeper and deeper

18 May 2000: Higher and higher


22 May 2000: The final depth

31 May 2000: The concrete flows


8 June 2000: Shuttering the tunnel walls

27 June 2000: Concrete to the tunnel walls


30 June 2000: Concrete to the tunnel walls 2

10 July 2000: The tunnel walls are ready


12 July 2000: Milano cathode system: cathode chamber, in front the flange to the gun

17 July 2000: Milano cathode system: cathode magazine


21 July 2000: Shuttering the tunnel ceiling

26 July 2000: The tunnel ceiling is ready


8 August 2000: The walls for the cooling area are coming into existence

17 August 2000: Removing the side walls of the pit


22 August 2000: The skeleton of the klystron hall

6 September 2000: The sides of the klystron hall


15 September 2000: The klystron hall and the cooling tower

22 September 2000: The gun cellar is ready


5 October 2000: Installing supply facilities

5 October 2000: Inside the klystron hall


10 October 2000: The cathode system arrives DESY Zeuthen

10 October 2000: The gun arrives DESY Zeuthen


12 October 2000: The transformer arrives DESY Zeuthen

17 October 2000: The measuring of the reference marks in the tunnel


31 October 2000: The klystron hall is ready

1 November 2000: The klystron tank


1 November 2000: The diagnostic section in the tunnel

1 November 2000: The cathode system in the tunnel


1 November 2000: The gun in the tunnel

15 November 2000: Thumbsketch of the gun


4 December 2000: One side of the hall and the cooling tower

7 December 2000: The klystron in the carrier


8 December 2000: Installation of the klystron